Harrisburg, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that a traffic shift will be implemented tonight at the Route 222/Route 30 Interchange Improvement Project in Manheim Township, Lancaster County. Eastbound Route 30 will be reduced from three lanes to two lanes from the Oregon Pike (Route 272) underpass to the Route 222 overpass. The right lane of eastbound Route 30 will be closed.
The Chester Road on-ramp to eastbound Route 30 will be shifted to the closed eastbound Route 30 right lane. This is expected to create congestion for eastbound Route 30 traffic exiting to northbound Route 222 and Chester Road traffic entering onto eastbound Route 30.
This long-term traffic shift is expected to be in effect for at least several months. There may be delays, especially during hours of peak traffic. Motorists should be alert.
Once the shift is in place, work on this project will be performed behind barrier during daytime hours.
The project includes improvements at the Route 222/Route 30 Interchange and reconstructing Route 222 from the interchange north approximately one mile near Stoner Park, which is just south of the Landis Valley Road bridge spanning the highway.
Work on the north side of the interchange includes constructing a second lane on the southbound Route 222 ramp to westbound Route 30 that will tie into the existing northbound Route 272 (Oregon Pike) exit ramp. A third lane will be added from the westbound Route 30 ramp to northbound Route 222 while extending this lane to the existing westbound Route 30 third lane approaching Oregon Pike (Route 272).
Work on the south side of the interchange includes constructing a second ramp lane from eastbound Route 30 to northbound Route 222. The new ramp lane will tie into the existing Route 30 travel lane (right lane), giving drivers using the right lane of eastbound Route 30 the option to continue east or exit to northbound Route 222.
Route 222 will be converted from four lanes to six lanes from the interchange to the north end of the project limits.
Additionally, the two bridges carrying Route 222 ramps over Route 30 will be replaced, with the northbound Route 222 bridge being widened to two lanes. The Eden Road bridge spanning Route 222 north of the interchange will remain in place. Route 222 under the bridge will be lowered to increase clearance under the bridge.
Four lanes of traffic will be maintained during the life of the project.
Motorists should be alert and drive with caution through the work zone.
This project is expected to be completed by September 3, 2027.
JD Eckman, Inc., of Atglen, PA, is the contractor on this $72,173,900 project.
Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following local alerts on X.
Subscribe to PennDOT news and traffic alerts in Adams, Cumberland, Dauphin, Franklin, Lancaster, Lebanon, Perry, and York counties at
PennDOT District 8.
Information about infrastructure in District 8, including completed work and significant projects, is available at
District 8 Results. Find PennDOT’s planned and active construction projects at
PennDOT Projects.
###