Sugar Run Road Intersection
Project Overview
The proposed project includes the construction of a single-lane roundabout at the Route 2003 (Sugar Run Road/Porter Street) and Route 2028 (Sugar Run Road) intersection in Franklin Township, Greene County. The project will also include the replacement of the existing bridge that carries Route 2028 (Sugar Run Road) over Sugar Run with a pre-cast reinforced concrete box culvert.
The project anticipates utilizing stagged construction. The first stage will demo the existing structure, install the proposed box culvert, and construct the eastern side of the roundabout while T-579 (Orchard Street) and Route 2028 (Sugar Run Road) are detoured (2.2 miles). The second stage will complete the roundabout while Route 2003 (Sugar Run Road) and Route 2003 (Porter Street) are detoured (8.5 mile) along with the detour from the first stage remaining in place.
The project is currently in Final Design.
Project Presentation
A PowerPoint presentation is available at the following link: Public Meeting Presentation (PDF)