Located in the Borough of Waynesburg – This $3.3 million project consists of the replacement of the existing structure carrying Route 21 over Toll Gate Run with a precast concrete box culvert. The contractor is Advanced Builders, Inc., and the project is anticipated to be complete in September 2024.
Project Update
09/09/2024 - The project is anticipated to restart work at the beginning of October. Work will involve relocating the waterline and installing a temporary stream diversion.
07/24/2024 – Project is still delayed. Utility is currently on site. No date has been established for project to restart construction.