Begin Main Content Area

​​​​​​

Route 318 ​Bridge Replacement Project

Beams are set in place for the Route 318 bridge. ​​

Project Overview

This project is to replace the bridge that carries Route 318 over Interstate 376 in Mercer County. 

The bridge was struck by the boom of a truck on the morning of December 7, 2023 and sustained substantial damage. For the safety of traffic traveling eastbound under the bridge, it was determined the damaged portion of the bridge should be removed as soon as possible. The spans over the westbound lanes remain intact. 

Bids for the contract to remove the remaining portion of the bridge and replace the entire structure were accepted from February 29 to March 14, 2024. Five bids were received.  Additional steps by the apparent low bidder must be completed before the contract is officially awarded. 

Once that step is complete, a work schedule, including a start date, will be confirmed by PennDOT and the contractor. 

The new bridge will have a higher vertical clearance of approximately 2 feet and will meet the current highway standards. It will be built at a similar roadway alignment as the former bridge. 

The project ​​will also include reconstruction of a portion of three of the interchange ramps, drainage upgrades, guiderail replacement, roadside signage, and pavement markings. Minor shoulder improvements and roadway repairs to Interstate 376 under the new bridge will also be completed. 

Route 318 Bridge location map.png

The bridge is located east of West Middlesex Borough and was built in 1966. Prior to the crash, it was rated in fair condition and was posted at 14 feet, 2 inches. It was used by approximately 3,200 vehicles a day, on average.

Traffic Impacts

A detour is currently in place for Route 318 traffic due to removal of the portion over the eastbound lanes of I-376. It is posted using Route 18 and Interstate 376 and will remain in place during construction. 

Near the end of the project, short-term detours of the ramps are anticipated in order to complete reconstruction work. 

A short-term closure of the westbound lanes of Interstate 376 will be needed to remove the remaining span of the bridge. A detour will be posted using off- and on-ramps near the bridge. Otherwise, short-term lane closures on Interstate 376 may be needed for certain construction activities.

A portion of the Route 318 bridge was demolished in December 2023.

Project Updates

6-17-24

Drivers are reminded that the Interstate 376 eastbound ramps at Exit 1C (Route 318, West Middlesex) are expected to be closed starting June 20, 2024. 

A detour will be posted using Route 18, Route 760, and I-376. The ramps are expected to reopen in August 2024. 

The closure is needed in order to complete work on Route 318 near the bridge and the eastbound ramps from and to I-376. The work will raise the profile of the roadway to meet the higher vertical clearance of the new bridge. 

Additionally, drivers may encounter daytime lane restrictions on I-376 near the bridge, as work requires. 

6-12-24

​Following the completion of work on the beams, construction will start on the roadway near the bridge and the eastbound ramps.

The off and on ramps at Exit 1C will be closed starting June 20, 2024. A detour will be posted using Route 18 and Route 760. The closure is expected to remain in place until mid-September. 

Route 318 bridge rebuild

4-21-24​

Route 318 bridge demo WB.JPG