​Bridge Authoring

For this phase of the directive, we are piloting the process of developing model-based deliverables for construction contracts using the OpenBridge Designer software, which includes analysis, 3D modeling and detailing tools. The objectives of this project are to develop a 3D model as complete as possible to reproduce the content traditionally conveyed through plan sheets; evaluate the Bentley software stack, and enable contractor use of the model.

Selected Pilot Projects:

​Project
District​County​SR-Section
Description​Let Date​
114138
​1
​Crawford
​1032-B00
​SR 1032 Bridge over Shirley Run
12/14/2023
8308
​4
​Lackawanna
​3006-250
​SR 3006 over Gardner Creek
07/27/2023